Bicycle Production Calendar and Peak Season Booking

Production time is the only part of an import order that cannot be bought back with money. You can pay for express freight, for a faster forwarder, for overtime — but you cannot pay a factory to have started three weeks earlier.

This page is the calendar logic for bicycle orders: how long an order really takes, how to count backwards from a shelf date, what peak season does to the numbers, and the five dates to put in writing.

How long an order actually takes

Need a quote on this? Send the model, quantity and destination port and we come back with FOB, MOQ and packing.

Stage What happens Typical span
Specification freeze Model, colour, components, marks signed off 1–2 weeks
Deposit and material booking Payment cleared, tubes and components ordered 1–2 weeks
Frame production Cutting, welding, painting 4–8 weeks
Assembly and QC Build, adjustment, inspection 2–3 weeks
Sailing Booking, loading, transit 4–7 weeks
Clearance and inland Documents, duty, delivery 1–3 weeks

Add the spans that apply to your order rather than taking the shortest line in each row. The shortest sum is not a plan; it is a promise.

The calendar, counted backwards

  1. Write the date the goods must be on the shelf, not the date they should arrive.
  2. Subtract clearance and inland delivery.
  3. Subtract sailing, using the sailing you actually have, not the best case.
  4. Subtract assembly and QC.
  5. Subtract frame and paint production.
  6. Subtract the deposit-to-material gap, plus a week for the money to clear.
  7. The number left is the latest date to freeze the specification.

That last date is the only one that matters in planning. Everything after it is consequence.

Peak season, in practice

Peak is not a price event; it is a capacity event. Three things change:

  • Paint slots fill first, because colour changes take line time.
  • Component supply tightens on the popular groupsets, which pushes substitution decisions.
  • Booking space gets scarce, so a late order waits for a sailing rather than a factory.

The practical response is to freeze specifications earlier than feels comfortable and to accept a substitution list in advance, so a component shortage changes a part rather than a date.

Five dates to put in writing

Date Who commits
Specification freeze Buyer
Deposit received Buyer and supplier
Production start Supplier
Inspection and loading window Supplier
Departure sailing Forwarder

An order without those five dates is a wish. With them, a delay becomes a documented fact rather than an argument.

Fast loading versus full private label

The two fastest ways to lose a loading date are a colour change late in production and private-label artwork that has not been approved. Both sit on the paint and marking line, which is the same line peak season already saturates.

  • Approve artwork before the deposit, not after it.
  • Limit colour changes to models where the volume justifies a paint slot.
  • Keep one “safe” colour per model that can be produced without a new set-up.

Reorder timing

The reorder date is not the season date; it is the date when cover falls to the lead time. With a twelve-week total lead time and a steady sell-through, the reorder is placed while the current stock still looks healthy — which is exactly when it feels unnecessary and exactly when it is needed.

Track three numbers per model: units sold per week, weeks of cover, and the planned departure sailing. When cover and sailing cross, the order is late.

If the sailing slips

It happens, and the response matters more than the delay. Three moves, in order: move the goods to the next sailing and re-book the inland delivery in the same email; tell the buyer the new shelf date with the cause, not the apology; and if the gap is long enough to hurt, split the shipment rather than holding all of it. A partial container on time plus a balance a month later usually protects the season better than one full container that arrives late.

What not to do is compress the remaining stages to make up time. Inspection and QC are the two stages that absorb the mistake, and cutting them converts a delay into a claim.

Where the calendar actually breaks

Orders rarely miss a shelf date in production. They miss it at one of five points, all of which are decided before the factory is involved:

Break point How it looks The move that saves it
Deposit clears late Material booked after the freeze date Count the bank’s clearing time inside the freeze date, not after it
Paint slot not booked A confirmed order with no line time Book the slot when the deposit is confirmed
Artwork approved late Marking queued behind peak colours Approve before the deposit, or accept a safe colour
Space booked late Goods ready, no sailing Book space at production start, not at loading
Inspection booked late A loading window without a report Book the inspection when assembly starts

None of these five is a factory delay, which is why chasing the factory does not recover them. The calendar is protected upstream, at the dates the buyer controls.

Questions buyers ask

How long is production?

Frame and paint four to eight weeks, assembly and QC two to three, with the exact figure set by the model and the colour plan.

When is peak season?

When paint slots and popular components are committed months ahead. Capacity, not price, is the constraint.

How much slack between production and sailing?

At least a week for inspection and a week for booking, more if the order includes private label marking.

Can I have a fast loading date and full private label?

Rarely in peak. Choose one; the other moves the date.

When should the reorder be placed?

When cover falls to the lead time, regardless of the calendar.

Next step

Send your shelf date and model list through the RFQ page and we will work back to the freeze date. Related: Incoterms for importers and LCL versus FCL.