The documents decide the landing, not the bike
Turkish import papers are issued per shipment. The RFQ takes model, quantity and port; the reply lists the invoice, packing list and certificate set for that destination.
A container of bicycles that clears customs two weeks late costs more than a container bought fifty dollars cheaper per unit. In Turkey the delay is almost never about the bicycles. It is about a file that does not match, a declaration made under the wrong code, or a document that arrives after the vessel.
This page is the working list we use with Turkish importers: what we issue, what you or your broker must issue, and the points where shipments actually get stuck.
Documents the factory issues
- Commercial invoice — model, quantity, unit price, FOB terms, and the exact model names used in the proforma
- Packing list — cartons per model, size and colour, net and gross weight, carton dimensions, total cubic metres
- Product specification sheet per model — frame, fork, wheels, brakes, drivetrain, and the assembly state
- Component list per model — the parts list your conformity file needs, with sizes
If your broker needs a certificate of origin or any other document issued through a chamber, tell us at the proforma stage. Some documents need to be applied for in advance and cannot be produced after the vessel sails.
Documents the importer arranges
Conformity assessment, registration where applicable, and the customs declaration itself are the importer’s responsibility under Turkish rules. Your broker decides which route applies to bicycles and to kids bicycles, which are treated under a different regime from adult bikes in most markets. We do not tell you which certificate you need, because that answer comes from your broker and your legal adviser, not from a factory.
The one thing we insist on: the model names, sizes and quantities on your declaration must be the same names, sizes and quantities on our invoice and packing list. A declaration written from a catalogue, while the container is packed from a confirmed proforma, is the most common reason a shipment sits.
Where Turkish shipments actually get stuck
- Model name drift. The buyer renames two models after the proforma. The invoice says the new names; the declaration was filed with the old ones. Two weeks.
- Missing conformity file. The broker is ready, the goods are ready, the conformity document is not. Nothing can be done from the factory side once the vessel has sailed.
- Carton count mismatch. The packing list says 412 cartons, the container holds 410 because two cartons were repacked at loading. This is avoidable: we photograph the loading and count before the doors close.
- Weight declaration. Gross weight differs from the declaration because the cartons were re-taped with heavier material. Small, but it stops a container.
- Late document release. Original documents sent by courier instead of released against payment, or telex release not instructed. This is a banking question, not a customs one, and it delays the container at the terminal, where storage starts charging.
Ports, terminals and the free time question
Izmir, Mersin and Istanbul (Ambarli) are the usual discharge ports for our Turkish shipments. Free time at destination is set by the shipping line and the terminal, not by us, and it is usually shorter than a buyer expects. Before booking, ask your forwarder for the actual free days at the named terminal and compare it with how long your clearance realistically takes. Detention and demurrage on a 40HQ accumulates daily and quietly, and it is the single most common unplanned cost on a first container.
What we photograph and hand over at loading
At loading we record: container number and seal, carton count per model, the loading sequence, and the condition of the cartons at the door. Photos go to the buyer before the vessel sails. That file is what makes a shortage or damage claim possible; without it, a claim becomes a conversation about trust.
The document calendar, worked backwards
For a shipment that must be in your warehouse by a fixed date:
- Production: 25–30 days from deposit and artwork approval (30–45 in peak season)
- Booking and loading: 3–7 days after production finishes
- Sailing to Izmir or Mersin: roughly 25–35 days
- Customs clearance: 3–10 days if the file is complete, longer if it is not
- Inland delivery to your warehouse: 1–3 days
From those numbers, a delivery date in May needs a deposit in January. That is not a sales tactic; it is the arithmetic of the route.
What to send your broker before the proforma is signed
Send the draft invoice and packing list to your broker before you pay the deposit. If the model names, the composition or the declared values need to change, it is cheaper to change them on a draft than to amend a declaration after the container has arrived.
Related reading: shipping documents checklist, detention and demurrage, bicycle wholesale to Turkey.
Import documents are a set, and a set only works if every document tells the same story. The table lists what the buyer usually has to assemble.
| Document | What it has to match | Where mismatch shows up |
|---|---|---|
| Commercial invoice | Model, quantity, unit price and trade term | Value disputes and delayed release |
| Packing list | Carton count, weights, marks and the model split | A container that cannot be verified against the invoice |
| Transport document | Consignee, port and the terms agreed | The cargo released to the wrong party |
| Certificate of origin | The origin claimed, prepared by the right party | Preferential treatment refused |
| Conformity documents | The models actually shipped, current | Release held pending documents |
| Insurance, if required | The value and the route insured | Losses falling on the buyer |
The classification question sits on top of this; how it is handled is on the HS code page.
Frequently asked questions
Do you issue a certificate of origin?
If your broker requires one, raise it at the proforma stage. Some documents must be applied for in advance and cannot be produced after the vessel sails.
Who handles Turkish conformity documents?
The importer, through its broker and adviser. We supply the specification sheet, component list and packing list that the file is built from.
Can model names on the invoice differ from the declaration?
They must not differ. Send the draft invoice to your broker before paying the deposit and settle the names there.
How much free time do we get at Izmir or Mersin?
That is set by the shipping line and terminal. Ask your forwarder for the free days at the named terminal before booking.
What do you send after loading?
Container number and seal, carton count per model, loading photos and carton condition at the door, before the vessel sails.
Next step
Send your destination port and model list to the RFQ page or bolunmaoyi@gmail.com, and we will return a draft invoice and packing list you can hand to your broker before the deposit.
Also for Turkey: private label for Turkish brands · kids bike size grid.
Category: wholesale programme — export terms, payment and shipping. · Site map