On this page
- Step one: written colour reference
- Step two: decal artwork, print-ready
- Step three: the frame template
- Step four: physical sample approval
- Step five: the golden sample and the standard
- Step six: production and in-process check
- What it costs, and what to agree in writing
- The mistakes that cost the most
- How this fits the order timeline
- Questions buyers ask
- Send us your order details
OEM orders fail in one of two places: the specification, and the approval. The specification failure is expensive but visible. The approval failure is cheap, invisible and has a habit of appearing after the container is loaded — a decal in the wrong shade, a logo two millimetres off centre, a colour that reads green under factory light and grey in the shop.
This is the workflow that prevents it, written from the factory side, so buyers know exactly what is being asked of them at each step.
Step one: written colour reference
Colour and decal approval is a staged process. Send model, quantity and destination port through the RFQ; the reply sets the proof rounds and the date the artwork must be fixed.
A colour name is not a specification. “Matte black” covers everything from a deep carbon black to a brownish soft black. What a factory can work with is a reference: a Pantone number, an existing sample sent to us, or a physical chip. Digital files are a starting point, not a decision — screens differ, and a PDF on a laptop is not a colour.
For powder coating specifically, ask for a physical panel sprayed in the chosen colour before the production run. It is the only reference that survives the gap between a screen and an oven.
Step two: decal artwork, print-ready
Decals need vector artwork, with the logo and text outlined where the printer cannot supply the font, and with dimensions tied to the frame. A design supplied as a photograph of a frame will be redrawn, and the redraw will not be your design.
State the process you expect — water transfer, UV transfer, or clear-coat overlaid — because a design that works in one process does not necessarily work in another. Thin hairlines and gradients behave differently depending on the process and the curvature of the tube.
Step three: the frame template
Decal position is set on a frame drawing or a template, not described in words. Where the head tube badge sits, where the top tube logo begins, how the down tube graphic wraps, where the seat tube mark is placed relative to the bottom bracket — all of it on a dimensioned drawing.
This is the step where “same as last time” is dangerous. If the frame geometry changed, the previous decal positions no longer hold, and the graphic will wrap badly on the down tube.
Step four: physical sample approval
Nothing is approved from a rendering. The factory paints and decals one frame or one set of tubes, photographs it in daylight, and ships the physical sample if the buyer wants it in hand. Approval is a written confirmation against that physical piece, not a chat message saying “looks good”.
A sample frame is money well spent. The cost of one frame, couriered, is small against the cost of a container of frames with a decal in the wrong place.
Step five: the golden sample and the standard
Once approved, that piece becomes the golden sample: the physical standard the production run is measured against. Keep a copy at the factory and, ideally, one with the buyer. Every subsequent production check compares against it rather than against a memory.
When the next order runs a year later, the golden sample is what stops the colour drifting a shade or two. That drift is normal across batches of powder; without a reference, nothing catches it.
Step six: production and in-process check
The first frames off the paint line are checked against the golden sample before the batch continues. Decal position is checked against the template. This is the cheapest moment to stop a mistake: the line is running and the correction is a re-set, not a repaint of finished goods.
What it costs, and what to agree in writing
OEM charges are quoted separately because they are setup work: artwork preparation, screen or transfer setup, colour matching, sample frame. There is normally a minimum quantity for a custom design, because the setups do not shrink with the order. Ask for the OEM cost as its own line with the minimum stated, so you can decide whether the design belongs on this container or a later one.
Agree in writing: who owns the artwork, whether the decal design is exclusive to you, whether we keep the screens for your next order, and what happens if a later order uses the same design. Exclusivity is a commercial term, not a technical one, and it should be on paper.
The mistakes that cost the most
Approving from a screen. Supplying artwork as a photo of a bike. Describing colour with a name instead of a reference. Skipping the sample frame to save two weeks. Splitting the design across three colours in the same run and approving only one. And the quiet one: never keeping a golden sample, so nobody can prove what was approved.
How this fits the order timeline
Approval is not inside the production window; it is before it. Our production runs 25 to 30 days, and 30 to 45 days in peak season, after the deposit clears and artwork is approved. Buyers who leave artwork approval until after the deposit frequently lose a week or two at the front of the calendar and then blame the lead time.
Start artwork while the proforma is being signed. It costs nothing to prepare and it protects the schedule.
Colour and decal approval is a sequence, and most delays come from running two steps at once. The table lists the steps and what each one locks.
| Step | What is produced | What it locks |
|---|---|---|
| Artwork file | Vector file with colour references stated as standards | The design source, independent of any monitor |
| Masking and layout | Decal placement mapped onto the actual frame shape | Position on tubes, and clearance around welds and joints |
| Colour panel | A painted panel in each colour, on the same substrate and finish | The colour itself, seen in daylight rather than on screen |
| Frame sample | One frame painted and decalled to the approved layout | How the design reads at full size |
| Batch proof | The first production frames photographed against the sample | Whether production matched approval, before packing |
| Written sign-off | Approval recorded with date and version number | Which version production is actually running |
Approval sits inside the wider sample process on the sample approval page.
Questions buyers ask
Can you match a Pantone colour?
Yes, given a Pantone reference or a physical sample. We spray a panel for approval before the run.
Do I need to approve a physical sample?
We strongly recommend it. Approval against a physical piece, not a rendering, is what prevents decal and colour errors.
Is there a minimum for custom decals?
Yes. Custom OEM work is quoted separately with a stated minimum, because the setup does not shrink with the order size.
Will you keep my artwork for the next order?
We keep the artwork and can rerun it, subject to the exclusivity terms agreed in writing with your order.
When should artwork be ready?
Before the deposit stage, so that production can start as soon as the deposit clears. Lead time runs from deposit and artwork approval, not from the enquiry.
Related guides
Before the artwork stage, read the sample policy for B2B buyers and carton specs and assembly ratio. Quotation lines are covered in quotation sheet pitfalls.
Send us your order details
For a wholesale quotation, tell us the models, quantities, size split, destination port and whether you need OEM branding. Write through the contact page or email bolunmaoyi@gmail.com. MOQ is 100 units per model, 30% deposit with the balance before loading, FOB Tianjin or Qingdao.