A mixed order is not one order; it is a set of small orders that have to share one line, one paint batch and one container. The allocation decision — which models run together, in what sequence, in what batch size — decides the delivery date more than the total quantity does.
This page covers how a mixed bicycle order is sequenced on the line, what a changeover costs, and what a buyer should ask before confirming a mixed container.
What allocation actually decides
Line allocation follows order size. Send model mix, units and destination port through the RFQ; the reply returns FOB with the line plan and the daily output we commit to.
| Decision | What it sets | What it costs if wrong |
|---|---|---|
| Model grouping | Which frames run back to back | Repeated fixture changes and idle time |
| Batch size per model | How long the line stays on one model | Too small: changeover dominates. Too large: schedule slips |
| Colour grouping | Paint batches and drying time | Short colour runs that cannot be repeated |
| Wheel and component readiness | Whether assembly can start | Frames waiting in the aisle for wheels |
| Packing order | The sequence cartons enter the container | Repacking at the loading bay |
Changeover, in plain terms
Every model change costs setup: fixture, programme, first-piece check, and the time before the line runs at speed again. The cost is roughly the same whether the batch is twenty bikes or two hundred, which is why a mixed order of six models at forty each is slower than two models at a hundred and twenty.
How a sensible sequence is built
- Group by frame platform first, then by size, then by colour.
- Run the deepest colour first in each group, so the paint shop has a full batch.
- Keep one buffer model that can run while a component is late.
- Set the packing sequence from the container plan, not from the production order.
What to ask before confirming
Four questions are enough: how many changeovers does the plan need, which model is the buffer, when does each colour batch run, and what is the cut-off date for adding a model without moving the delivery. The answers are the difference between a plan and a hope.
What a mixed container does to the date
The delivery date is set by the last model, not the total quantity. A mixed order of five models needs five setups, five first-piece checks and five colour batches; the buyer sees one container and the factory sees five short runs.
- Ask for the schedule by model, with the setup date for each.
- Identify the buffer model that can absorb a late component.
- Keep the container plan and the production sequence in the same order.
- Fix the last date a model can be added without moving loading.
A supplier who can name those four items has planned the order. A supplier who answers with a single delivery date has quoted it.
Questions buyers ask
Can a mixed OEM order really finish in 25 to 30 days?
It can in normal season when the decals are approved before the paint slot and no component is on allocation. In peak season the same mix takes 30 to 45 days, and the honest answer depends on what else is booked on the line that week.
Should I ask for a schedule by model or one delivery date?
Ask by model and by week, with frame, paint, assembly and packing dates. One delivery date hides which model is at risk, and the risk is almost always one model, not the whole order.
What happens if one model is late at loading time?
Either the container is held until the model is ready, or it is loaded partial and the rest ships later. Agree which rule applies before the deposit; a supplier deciding this alone usually decides it in their own favour.
Does a bigger quantity get a better slot?
Sometimes, because a large run justifies a dedicated paint slot. But a large order that is unapproved sits in the same queue as a small one. Approval timing matters more than quantity in peak season.
Can I change the size breakdown after production starts?
Only within what has not been cut or painted. Frame sizes are cut in batches, so a size change after cutting usually means new frames and a new date. Confirm the breakdown before the frame slot.
Related guides
- Factory Visit Agenda for Bicycle Buyers in China
- Bicycle Production Calendar and Peak Season Booking
- Bicycle Order Amendments: What Each Change Costs
Send us your order details
If you are building a range and want a price against a real specification, send the model list, the quantity per model, the destination port and whether the order is OEM or our own decals. We quote on that, not on a photo. Write to our contact page or bolunmaoyi@gmail.com.
Working terms: MOQ 100 units per model, 30 percent deposit with the balance before loading, 25 to 30 days in normal season and 30 to 45 days in peak season, FOB Tianjin or Qingdao. CIF and DAP are quoted separately.