PDI is a different inspection from the factory one
Receiving inspection is planned before the container lands. Put model, quantity and destination port in the RFQ; the reply sets the PDI sheet and who signs it at the dealer end.
Factory inspections — DUPRO, PSI, container loading check — happen before the container leaves. PDI happens after it lands, in your warehouse, before a bike reaches a customer. They answer different questions: the factory inspection asks whether the production run matches the approved sample; PDI asks whether what arrived is what you paid for, and whether each unit can be sold after assembly.
Buyers who skip PDI usually discover the problems through dealers, one complaint at a time, weeks after the container is unloaded. The cost is not the part; it is the labour, the freight on a replacement and the conversation with the dealer.
Before you open a single carton
The first hour decides how much of the claim you can still prove:
- Check the seal and the container number against the bill of lading and photograph both before the doors open.
- Count cartons against the packing list while they come out, model by model — not after they are stacked in the warehouse.
- Photograph damage as found: crushed cartons, water stains, torn strapping, pallets that moved. Once the cartons are restacked, the evidence is gone.
- Note the condition on the delivery receipt before signing. A clean receipt with damage found later is a weaker claim.
Shortage and transit damage are claims against the carrier or the insurer, not the factory. They need their own evidence set and their own deadline, which is usually much shorter than a quality claim.
Carton level, then unit level
Two passes keep the work manageable:
- Carton pass — 100%. Every carton is counted, checked for damage, and matched to the model and carton mark on the packing list. This is fast and catches shortages and mis-shipments immediately.
- Unit pass — every unit before sale. Open, inspect the frame and fork, check the parts bag, and record the frame number. For a dealer this is the PDI that protects the warranty; for a distributor it is the gate before the bike goes into stock.
If you cannot inspect every unit on arrival, inspect a sample to confirm the batch is sound, then complete the unit pass at the point of assembly or dispatch. What you should not do is assume the carton count is the inspection.
The twelve points that actually fail
| Check | What goes wrong |
|---|---|
| Frame and fork alignment | Dropout spacing off, fork bent in transit — visible once the wheels are fitted |
| Frame number and model code | Missing, duplicated or not matching the packing list |
| Paint and decals | Scuffs from packing, decal misaligned or missing on one side |
| Wheel trueness | Spokes loosened in transit; rim contact on the brake pads |
| Brake set-up | Pads rubbing, cable tension wrong, disc rotor offset |
| Drivetrain | Chain length, derailleur hanger bent, shifting off by one index |
| Torque on stem and seatpost | Under-torqued from the line, or over-torqued and cracking the clamp |
| Headset play | Rocking under load once the fork is fitted |
| Parts bag completeness | Pedals, reflectors, bell, tools or manual missing |
| Accessories fitted to order | Kickstand, rack, mudguard or basket missing where the order specified them |
| Tyre seating and pressure | Bead not seated, tube pinched during packing |
| Carton marks and labels | Wrong model on the carton, missing shipping mark, no barcode |
Twelve points, roughly fifteen to twenty minutes per unit for someone who knows the product. That number is the basis for the staffing plan below.
The staffing maths on a 350-bike container
A 40HQ usually carries about 350 mountain bikes in the 26-inch range. At 20 minutes per unit:
- 350 × 20 minutes = 7,000 minutes ≈ 117 hours;
- one technician at 8 productive hours a day: about 15 working days;
- two technicians: about 7 to 8 working days;
- the carton pass, done properly, adds roughly one day for two people.
If the container arrives two weeks before your season starts and you have one technician, the plan is already late. Either book the labour or accept sample-based inspection and finish the unit pass at dispatch — but decide before the container lands, not after.
When something is wrong
Quality claims are won on evidence, not on volume of emails. For each defect, record:
- frame number or carton number;
- model and production batch if it is on the carton;
- a photograph of the defect and a photograph of the carton label;
- quantity affected against quantity received.
Then the commercial decision: replacement parts in the next shipment, a credit, or a return. Parts are usually the cheapest fix; returns across an ocean rarely are. Agree the claim window in the purchase contract — a common structure is a defined period after arrival, with transit damage handled separately by the carrier. Our claim flow is written up in warranty claims and spare parts flow.
Questions buyers ask
Do we need to open every carton?
Count and check every carton, yes. Opening every unit is ideal but not always practical; if you sample on arrival, complete the unit pass before the bike is sold or assembled for a customer.
Who pays for defects found at PDI?
It depends on the cause and the contract. Manufacturing defects are a supplier claim; transit damage is a carrier or insurance claim. The evidence set and the deadline are different for each.
How long do we have to claim?
Whatever the purchase contract says, and it should be a defined number of days after arrival. Transit damage deadlines are usually much shorter and set by the carrier.
Can PDI be done by the dealer instead?
It can, but then the distributor loses the chance to catch a batch problem before it spreads across ten dealers. A sample check at the warehouse plus a full check at the dealer is a workable split.
What is the most common failure?
In our experience it is small: brake rub, missing parts-bag items and carton damage. They are cheap to fix at the warehouse and expensive to fix after the customer has the bike.
Next step
If you want the PDI sheet in your own language, ask for it with the order — we can supply the twelve-point list and the packing list format that matches it. Send the models and quantities to the RFQ page. For the loading side, read container loading supervision and the carton packaging checklist.